Data-Centre Diesel Replacement
Two very different questions, kept apart on purpose: displacing standby diesel that runs a few dozen hours a year, and supplying firm baseload that runs all year.
National context, display only. Australian data-centre electricity consumption was about 3.9 TWh in FY25, and about 21.4 TWh by 2035 under AEMO’s accelerated-growth scenario (AEMO / Oxford Economics). The 2035 figure is a named scenario forecast, not a fact. Neither figure is an input to anything calculated on this page: a national aggregate cannot size a site.
Annual energy from generators
—
—
Annual diesel volume
—
—
Annual diesel fuel cost
—
—
Annual Scope 1 CO2-e
—
—
On-site fuel storage implied by the runway
—
—
1 MWe units to cover the load
—
—
What this scenario does and does not show
—
—
Unity Battery capital + service charge case company-stated
—
—
Cost difference over the period
—
—
Cumulative-cost crossover
—
—
Cumulative cost — on-site diesel fuel vs the Unity Battery case
The diesel side counts fuel only — no generator capital, maintenance or replacement. The Unity side uses company-stated planning figures; no unit has been sold or delivered commercially at these prices. Unit count covers the load only, with no N+1 or 2N redundancy, which no real data centre would accept.
Constraints that this arithmetic does not capture
- Redundancy is not assumed. Unit counts cover the load only. Data centres are built to N+1 or 2N standards, so a real installation would need more units than shown. No redundancy configuration is proposed or costed here.
- Standby diesel is not primarily an energy cost. Its function is ride-through and resilience. Displacing it changes the resilience architecture, which is a design and assurance question, not an arithmetic one.
- Start-up and load-following behaviour differ. Standby diesel is specified on its ability to pick up load in seconds. No claim is made about the Unity Battery’s transient response, and no independently verified data exists on it.
- Uptime certification. Tier certification, insurer requirements and customer contractual SLAs constrain what plant may be relied upon. None of these have been assessed for a reactor at an Australian data centre, where the technology is in any case currently prohibited.
- Nothing here is a facility design. No Australian data centre has an approval pathway for on-site nuclear generation.
Method
The formulas, in full
The two scenarios use the same engine with different running hours. They are presented separately because combining them produces a misleading result: applying baseload running hours to a standby fleet overstates avoidable fuel cost by two orders of magnitude.
Emissions use the DCCEEW-derived Scope 1 factor of 2.710 kg CO2-e per litre. Scope 2 grid emissions are not netted off, because in the firm baseload scenario the counterfactual mix is site-specific and no like-for-like study is presented here.
In the backup scenario no cost is attributed to the Unity Battery side, because standby plant is a resilience asset and a fuel-cost comparison would mislead. The firm baseload scenario carries an illustrative comparison built from company-stated planning figures (US$10M per 1 MWe unit plus US$350k per unit per year), badged as unverified. For the fuller total-cost treatment see Module 5.
Provenance
Constants and sources
General information only
This calculator provides general, illustrative information only about hypothetical energy-generation scenarios. It does not take into account your personal circumstances, objectives or financial situation, and does not constitute financial product advice, an offer of securities, or a recommendation to invest in Deployable Energy Fund Limited, Deployable Energy Limited, or any other entity. Figures are drawn from third-party Australian government, regulator and industry sources (cited on this page) and, where expressly badged, from Deployable Energy’s own unverified planning assumptions. They are provided for general educational and illustrative purposes only. The Unity Battery microreactor has not yet been deployed commercially, and civilian nuclear power generation is not currently permitted in Australia under the EPBC Act and the ARPANS Act (and, in several states, additional state legislation). Nothing on this page should be relied upon as a representation that deployment in Australia is imminent or currently lawful.